1. |
A and B can do a piece of work in 5 days ; B and C can do it in 7 days; A and C can do it in 4 days. Who among these will take the least time. If put to do it alone ? |
A. | A |
B. | B |
C. | C |
D. | Data inadequate |
Answer» B. B | |