1. |
A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in? |
A. | 12 days |
B. | 13(5/7) days |
C. | 13 days |
D. | 13(3/4) days |
Answer» E. | |