1. |
A alone can complete a work in 16 days and B alone can do in 12 days. Starting with A, they work on alternate days. The total work will be completed in? |
A. | 13(1/4) |
B. | 13(1/2) |
C. | 13(3/4) |
D. | 13 |
Answer» D. 13 | |