A alone can complete a work in 16 days and B alone in 12 days. starting with A , they work on alternative days. the total work will be completed in _____________

A. 96/7 DAYS
B. 12 DAYS
C. 55/4 DAYS
D. 13 DAYS
Answer» D. 13 DAYS