1.

4 men and 6 women complete a work in 8 days, 2 men and 9 women also complete in 8 days. The number of days 18 women complete the work is:

A. 4 1/3 days
B. 5 1/3 days
C. 5 2/3 days
D. 4 2/3 days
Answer» C. 5 2/3 days