MCQOPTIONS
Saved Bookmarks
1. |
12 men can complete a work in 18 days. Six days after they started working, 4 men joined them. How many days will of them take to finish the remaining work ? |
A. | 9 |
B. | 10 |
C. | 12 |
D. | 15 |
Answer» B. 10 | |