MCQOPTIONS
Saved Bookmarks
1. |
12 children take 16 days to complete a work which can be completed by 8 adults in 12 days. 16 adults started working and after 3 days 10 adults left and 4 children joined them. How many days will it take them to complete the remaining work? |
A. | 6 |
B. | 8 |
C. | 4 |
D. | 3 |
Answer» B. 8 | |