Explore topic-wise MCQs in Civil Engineering.

This section includes 11 Mcqs, each offering curated multiple-choice questions to sharpen your Civil Engineering knowledge and support exam preparation. Choose a topic below to get started.

1.

For making bund ordinary mud wall gonda ( bund) about 8” * 6” shall be made on the sides.

A. True
B. False
C.
Answer» B. False
2.

AVERAGE_NUMBER_OF_BLOCKS_REQUIRED_FOR_A_TWO-ROOMED_HOUSE_IS_ABOUT_2500.?$

A. True
B. False
Answer» B. False
3.

For preparation of subgrade the existing subgrade should be dressed to a camber of 1 in 24 to 1 in 32.$

A. True
B. False
Answer» B. False
4.

Before_applying_water_proof_mud_plaster,_the_joints_should_not_be_scrapped.$

A. True
B. False
Answer» C.
5.

For making bund ordinary mud wall gonda ( bund) about 8” * 6” shall be made on the sides.$

A. True
B. False
Answer» B. False
6.

The roofing cannot be made with slate?

A. True
B. False
Answer» C.
7.

Stabilized soil wall is cued for ______ to ______ days by sprinkling water.

A. 3 to 6
B. 15 to 20
C. 7 to 10
D. 20 to 35
Answer» D. 20 to 35
8.

The excavation exceeding 1.5 m in width and 10 sq. m in plan area with a depth not exceeding 30 cm, is termed as __________

A. excavation
B. surface dressing
C. surface excavation
D. cutting
Answer» D. cutting
9.

The brick work is not measured in cu m in case of __________

A. one or more than one brick wall
B. brick work in arches
C. reinforced brick work
D. half brick wall
Answer» E.
10.

For fourth class building roofing shall be of __________over bamboo and wooden supports.

A. mud roof
B. tile roof
C. wooden roof
D. bamboo roof
Answer» C. wooden roof
11.

The water proof mud- plaster consists of _______________

A. soil
B. janta Emulsion
C. cowdung
D. soil, janta emulsion and cowdung
Answer» E.