51.

Which one of the following methods is generally used for the layout of the muck-car tracks

A. the grass hopper method
B. passing track method
C. the cherry picker
D. California crossing, Dixon conveyor
Answer» E.
52.

The difference of heights of the tunnels above rail tops of BG and MG tracks is kept

A. 0.30 m
B. 0.45 m
C. 0.60 m
D. 0.75 m
Answer» D. 0.75 m
53.

A tunnel is found more advantageous as compared to the alternate routes because it:

A. remains free from snow
B. reduces the cost by reducing the route distance
C. reduces the maintenance cost
D. avoids interference with surface rights
Answer» E.
54.

Which one of the following statements is not correct in respect of setting of an inclined tunnel:

A. Reference points are constructed at every 300 m.
B. The alignment is fixed from upper/lower apex point.
C. The level of the invert at the heading is marked by a tape.
D. Reference points are constructed on the roof of tunnels
Answer» E.
55.

High pressure grouting is generally restored for concreting in the lining if the rock strata is:

A. highly fissured
B. poor
C. likely to get seepage of water
D. All of the above.
Answer» E.
56.

For B.G. single track railway, the height of the tunnel above top of rails should be

A. 5.5 m to 5.8 m
B. 5.8 m to 6.2 m
C. 6.7 m to 7.3 m
D. 7.3 m to 7.5 m
Answer» D. 7.3 m to 7.5 m
57.

Which one of the following statements is not correct for heading and benching method of tunnelling ?

A. Drilling and mucking can be done simultaneously
B. Benching provides a plateform for working on heading
C. Removal of muck from the heading is very easy
D. None of these.
Answer» D. None of these.