1.

What is the flight speed assumed while designing a rectangular tank?

A. t0.1r/min
B. t0.2-0.5 r/min
C. t0.6-1.2 r/min
D. t1.2-1.5 r/min
Answer» D. t1.2-1.5 r/min
2.

What is the flight speed assumed while designing a circular tank?

A. t0.01r/min
B. t0.02-0.05 r/min
C. t0.06 r/min
D. t0.06-0.09 r/min
Answer» C. t0.06 r/min
3.

What is the detention time considered while designing a primary sedimentation tank which is followed by an activated sludge treatment tank?

A. t1hr
B. t1.5-2.5hrs
C. t3hrs
D. t3-4hrs
Answer» C. t3hrs
4.

In a primary sedimentation tank in percentage what is the amount of TSS removed?

A. t40-50%
B. t50-70%
C. t80%
D. t85%
Answer» C. t80%