Explore topic-wise MCQs in Manufacturing Engineering.

This section includes 17 Mcqs, each offering curated multiple-choice questions to sharpen your Manufacturing Engineering knowledge and support exam preparation. Choose a topic below to get started.

1.

Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs.30. The break even quantity between the two alternatives is

A. 25
B. 50
C. 75
D. 100
Answer» C. 75
2.

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300
B. 40
C. 500
D. 1000
Answer» D. 1000
3.

M.T.M is used to

A. improve existing methods
B. establish time standards
C. develop effective methods in advance of the beginning of production
D. all of the mentioned
Answer» E.
4.

P.M.T.S( Predetermined Motion Time System) include

A. M.T.M (Method Time Measurement)
B. W.F.S (Work Factor Systems)
C. B.M.T.S (Basic Motion Time Study)
D. All of the mentioned
Answer» E.
5.

MRP-II system is called a closed loop system because it considers

A. inventory
B. finance
C. man power
D. none of the mentioned
Answer» C. man power
6.

M.T.M_IS_USED_TO?$

A. improve existing methods
B. establish time standards
C. develop effective methods in advance of the beginning of production
D. all of the mentioned
Answer» E.
7.

Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs.30. The break even quantity between the two alternatives is$

A. 25
B. 50
C. 75
D. 100
Answer» C. 75
8.

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be$

A. 300
B. 40
C. 500
D. 1000
Answer» D. 1000
9.

P.M.T.S( Predetermined Motion Time System) includ?

A. M.T.M (Method Time Measurement)
B. W.F.S (Work Factor Systems)
C. B.M.T.S (Basic Motion Time Study)
D. All of the mentioned
Answer» E.
10.

MRP-II system is called a closed loop system because it consider?

A. inventory
B. finance
C. man power
D. none of the mentioned
Answer» C. man power
11.

Capacity planning is concerned with

A. how many machines required
B. how much labour required
C. all of the mentioned
D. none of the mentioned
Answer» D. none of the mentioned
12.

CRP takes material requirements from MRP and converts to

A. standard hours of man power
B. standard hours of machine
C. standard hours of load
D. all of the mentioned
Answer» E.
13.

Forecasting is used for

A. dependent demand items
B. independent demand items
C. all of the mentioned
D. none of the mentioned
Answer» C. all of the mentioned
14.

Just in time manufacturing philosophy emphasizes on

A. man power
B. manufacturing
C. profit
D. inventory
Answer» E.
15.

Bill of material structure is used to

A. calculate net requirements
B. calculate due dates
C. calculate man power requirements
D. all of the mentioned
Answer» B. calculate due dates
16.

Inventory record file gives the following information

A. lot size
B. machine details
C. customer name
D. none of the mentioned
Answer» B. machine details
17.

The basic difference between MRP and MRP-II is:

A. inventory
B. bom
C. finance
D. capacity planning
Answer» D. capacity planning