1. |
What is the depth the needle in Vicat apparatus should penetrate into the cement paste in consistency test? |
A. | 33-35 cm from bottom of the mould |
B. | 33-35 mm from top of the mould |
C. | 33-35 cm from top of the mould |
D. | 33-35 mm from bottom of the mould |
Answer» C. 33-35 cm from top of the mould | |
2. |
Green cement is: |
A. | Green coloured cement |
B. | Cement mixed with plant products |
C. | Cement mixed with recycled materials |
D. | Cement mixed with green algae |
Answer» D. Cement mixed with green algae | |
3. |
Wet cement can cause severe skin burns if not washed off with water immediately. |
A. | True |
B. | False |
Answer» B. False | |
4. |
Use of coarser cement particles leads to: |
A. | Low durability |
B. | Higher strength |
C. | Low consistency |
D. | Higher soundness |
Answer» B. Higher strength | |
5. |
USE_OF_COARSER_CEMENT_PARTICLES_LEADS_TO:?$ |
A. | Low durability |
B. | Higher strength |
C. | Low consistency |
D. | Higher soundness |
Answer» B. Higher strength | |
6. |
Green cement is:$ |
A. | Green coloured cement |
B. | Cement mixed with plant products |
C. | Cement mixed with recycled materials |
D. | Cement mixed with green algae |
Answer» D. Cement mixed with green algae | |
7. |
Wet_cement_can_cause_severe_skin_burns_if_not_washed_off_with_water_immediately.$ |
A. | True |
B. | False |
Answer» B. False | |
8. |
What_is_the_depth_the_needle_in_Vicat_apparatus_should_penetrate_into_the_cement_paste_in_consistency_test? |
A. | 33-35 cm from bottom of the mould |
B. | 33-35 mm from top of the mould |
C. | 33-35 cm from top of the mould |
D. | 33-35 mm from bottom of the mould |
Answer» C. 33-35 cm from top of the mould | |
9. |
What is the initial setting time of cement? |
A. | 1 hour |
B. | 30 minutes |
C. | 15 minutes |
D. | 30 hours |
Answer» C. 15 minutes | |
10. |
Which equipment is used to test the setting time of cement? |
A. | Core cutter |
B. | Vibrator |
C. | Universal testing machine (UTM) |
D. | Vicat apparatus |
Answer» E. | |
11. |
Which of the below mentioned is not a result of field test performed on cement? |
A. | There should not be any lumps |
B. | It should feel cold when you put your hand in bag of cement |
C. | The colour should be blackish grey |
D. | It should not be gritty when rubbed with finger |
Answer» D. It should not be gritty when rubbed with finger | |
12. |
Time elapsed from the instance of adding water until paste ceases to behave as fluid is called: |
A. | Initial setting time |
B. | Final setting time |
C. | Intermediate setting time |
D. | Absolute setting time |
Answer» B. Final setting time | |
13. |
What is the meaning of soundness of cement? |
A. | Ability to flow when mixed |
B. | Ability to make ringing noise when struck |
C. | Ability to form strong and sound structure |
D. | Ability to retain volume after setting. |
Answer» E. | |
14. |
What is the average particle size of cement? |
A. | 15 microns |
B. | 45 microns |
C. | 75 microns |
D. | 100 microns |
Answer» B. 45 microns | |
15. |
Who invented Portland cement and in which year? |
A. | William Aspdin, 1824 |
B. | William Aspdin, 1840s |
C. | Joseph Aspdin, 1840s |
D. | Joseph Aspdin, 1824 |
Answer» C. Joseph Aspdin, 1840s | |
16. |
Why is natural cement used very limitedly? |
A. | Brown in Colour |
B. | Standard consistency is not met with |
C. | Sets too quickly |
D. | Particle size is too fine |
Answer» D. Particle size is too fine | |