101.

Micromotion study involves following number of fundamental hand motions_______________?

A. 8
B. 12
C. 16
D. 20
E. 24
Answer» D. 20
102.

Micro motion study is__________________?

A. analysis of a man-work method by using a motion picture camera with a timing device in the field of view
B. motion study* observed on enhanced time intervals
C. motion study of a sequence of operations conducted systematically
D. study of man and machine conducted simultaneously
E. scientific, analytically procedure for determining optimum work method
Answer» B. motion study* observed on enhanced time intervals
103.

Merit Rating is the method of determining worth of_______________?

A. a job
B. an individual employee
C. a particular division in workshop
D. machine
E. overall quality
Answer» C. a particular division in workshop
104.

Material handling in automobile industry is done by_________________?

A. overhead crane
B. trolley
C. belt conveyor
D. all of the above
E. none of the above
Answer» B. trolley
105.

Material handling and plant location is analysed by________________?

A. Gnatt chart
B. bin chart
C. Emerson chart
D. travel chart
E. activity chart
Answer» E. activity chart
106.

Job enrichment technique is applied to_________________?

A. reduce labour monotony
B. overcome boring and demotivating work
C. make people happy
D. all of the above
E. none of the above
Answer» E. none of the above
107.

Job evaluation is the method-of determining the________________?

A. relative worth of jobs
B. skills required by a worker
C. contribution of a worker
D. contribution of a job
E. effectiveness of various alternatives
Answer» B. skills required by a worker
108.

Inventory management consists of__________________?

A. effective running of stores
B. state of merchandise methods of stroing and maintenance etc
C. stock control system
D. all of the above
E. none of the above
Answer» E. none of the above
109.

Inventory control in production, planning and control aims at________________?

A. achieving optimisation
B. ensuring against market fluctuations
C. acceptable customer service at low capital investment in inventory
D. discounts allowed in bulk purchase
E. regulate supply and demand
Answer» D. discounts allowed in bulk purchase
110.

In which of the following layouts, the lines need to the balanced_______________?

A. process layout
B. product layout
C. fixed position layout
D. plant layout
E. functional layout
Answer» C. fixed position layout
111.

In the perpetual inventory control, the material is checked when it reaches its________________?

A. minimum value
B. maximum value
C. average value
D. alarming value
E. original value
Answer» B. maximum value
112.

In the Halsey system of wage incentive plan, a worker is ________________?

A. paid as per efficiency
B. ensured of minimum wages
C. not paid any bonus till his efficiency
D. never a loser
E. induced to do more work
Answer» C. not paid any bonus till his efficiency
113.

In the Halsey 50-50 plan, the following are rewarded more___________________?

A. past good workers
B. past poor workers
C. past average workers
D. all of the above
E. none of the above
Answer» C. past average workers
114.

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches__________________?

A. 50%
B. 661%
C. 75%
D. 80%
E. 90%
Answer» C. 75%
115.

In steel plant the most important system for materials handling is_____________________?

A. conveyors
B. cranes and hoists
C. trucks
D. locos
E. none of the above
Answer» E. none of the above
116.

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if_________________?

A. complete details’of items in, waiting line are known
B. arrival and waiting times are known and can be grouped to form a waiting line model
C. all variables and constants are known and form a linear equation
D. the laws governing arrivals, service times, and the order in which the arriving units are taken into source are known
E. all of the above
Answer» E. all of the above
117.

In PERT analysis, critical path is obtained by joining events having___________________?

A. +ve slack
B. -ve slack
C. zero slack
D. dummy activities
E. critical activities
Answer» D. dummy activities
118.

In perpetual inventory control, the material is checked as it reaches its__________________?

A. minimum value
B. maximum value
C. average value
D. middle value
E. alarming value
Answer» B. maximum value
119.

In order that linear programming techniques provide valid results________________?

A. relations between factors must be linear (positive)
B. relations between factors must be linear (negative)
C. A. or B.
D. only one factor should change at a time, others remaining constant
E. none of the above
Answer» D. only one factor should change at a time, others remaining constant
120.

In micromotion study, therblig is described by_______________?

A. a symbol
B. an event
C. an activity
D. micro motions
E. standard symbol and colour
Answer» F.
121.

In Lincoln plan (one type of group incentive plan), the amount of the profit which an .employee receives in addition to the guaranteed basic _________________?_x005F_x000D_pay/wages, is based on :

A. a standard rating system
B. a merit rating system
C. a job evaluation system
D. his individual performance
E. all of the above
Answer» C. a job evaluation system
122.

In inventory control, the economic order quantity is the_________________?

A. optimum lot size
B. highest level of inventory
C. lot corresponding to break-even point
D. capability of a plant to produce
E. none of the above
Answer» B. highest level of inventory
123.

In Halsey 50-50 plan, output standards are established______________?

A. by time study
B. from previous production records
C. from one’s judgement
D. all of the above
E. none of the above
Answer» C. from one’s judgement
124.

In a PERT chart___________________?

A. all activities should be numbered
B. only important activities should be numbered
C. only critical activities are numbered
D. only selected activities are numbered
E. no activity is numbered
Answer» B. only important activities should be numbered
125.

In A-B-C control policy, maximum attention is given to__________________?

A. those items which consume money
B. those items which are not readily available
C. those x items which are in more demand
D. those items which consume more money
E. proper quality assurance program-mes
Answer» E. proper quality assurance program-mes
126.

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?

A. latest start time – earliest start time
B. latest finish time – earliest finish time (EFT)
C. TL-EFT
D. all of the above
E. none of the above
Answer» E. none of the above
127.

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?

A. EF=ES+D
B. LS=LF-D
C. LF = LS + D
D. D = EF-ES
E. all of the above
Answer» F.
128.

If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be______________________?

A. 2 HA
B. 1.33 HA
C. 1.5 HA
D. 1.15 HA
E. 2.5 HA
Answer» B. 1.33 HA
129.

Graphical method, simplex method, and transportation method are concerned with__________________?

A. break-even analysis
B. value analysis
C. linear programming
D. queing theory
E. tnaterial handling
Answer» D. queing theory
130.

Gnatt charts provide information about_____________?

A. break even point analysis
B. production schedule
C. material handling layout
D. determining selling price
E. value analysis
Answer» C. material handling layout
131.

Gnatt charts are used for_________________?

A. forecasting sales
B. production schedule
C. scheduling and routing
D. linear programming
E. none of the above
Answer» C. scheduling and routing
132.

Gnatt chart provides information about the________________?

A. material handling
B. proper utilisation of manpower
C. production schedule
D. efficient working of machine
E. all of the above
Answer» D. efficient working of machine
133.

Frederick W. Taylor introduced a system of working known as________________?

A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation
E. none of the above
Answer» D. effective organisation
134.

For ship vessel industry the following layout is best suited_________________?

A. process layout
B. product layout
C. fixed position layout
D. plant layout
E. functional layout
Answer» D. plant layout
135.

For a product layout the material handling equipment must _________________?

A. have full flexibility
B. employ conveyor belts, trucks, tractors etc
C. be a general purpose type
D. be designed as special purpose for a particular application
E. arranging shops according to specialization of duties
Answer» E. arranging shops according to specialization of duties
136.

Father of time study was_________________?

A. F.W. Taylor
B. H.L. Gantt
C. F.B. Gilberfh
D. R.M. Barnes
E. H.B. Maynord
Answer» B. H.L. Gantt
137.

Father of industrial engineering is_________________?

A. Jeck Gilberth
B. Gnatt
C. Taylor
D. Newton
E. none of the above
Answer» C. Taylor
138.

Expediting function consists in keeping a watch on__________________?

A. operator’s activity
B. flow of material and in case of trouble locate source of trouble
C. minimising the delays
D. making efficient despatching
E. none of the above
Answer» C. minimising the delays
139.

Emergency rush order can be pushed more effectively in__________________?

A. job production
B. automatic production
C. continuous production
D. intermittent production
E. none of the above
Answer» E. none of the above
140.

Descripancies of bar chart techniques are________________?

A. consequential effects of lack in one activity on omer
B. consequential effects of lack in one activity on the finish date
C. free time available for an activity can’t be predicted
D. effective monitoring/controlling can’t be done
E. all of the above
Answer» F.
141.

Current assets include_______________?

A. manufacturing plant
B. manufacturing plant and equipment
C. inventories
D. common stock held by the firm
E. all of the above
Answer» B. manufacturing plant and equipment
142.

Criticalpath on PERT/CPM chart is obtained by joining the events having____________________?

A. maximum slack
B. minimum slack
C. average slack
D. no slack
E. judgement and experience
Answer» C. average slack
143.

Critical Path Net Work helps an engineer_________________?

A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all of the above
E. none of the above
Answer» E. none of the above
144.

Critical path moves along the activities having total float of_____________________?

A. positive value
B. negative value
C. zero value
D. same value
E. none of the above
Answer» D. same value
145.

CPMis___________________?

A. synthesising in concepts
B. is built of activities oriented program-mes
C. is, based on one time eytimate
D. is used for repetitive works
E. all of the above
Answer» F.
146.

CPM is the___________________?

A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique
Answer» D. target oriented technique
147.

CPM has following time estimate__________________

A. one time estimate
B. two time estimate
C. three time estimate
D. four time estimate
E. nil time estimate
Answer» B. two time estimate
148.

Choose the wrong statement Time study is used to_________________?

A. determine overhead expenses
B. provide a basis for setting piece prices or incentive wages
C. determine standard costs
D. determine the capability of an operator to handle the number of machines
E. compare alternative methods
Answer» B. provide a basis for setting piece prices or incentive wages
149.

Break-even analysis can be used for__________________?

A. short run analysis
B. long run analysis
C. average of above two run analysis
D. there is no such criterion
E. none of the above
Answer» B. long run analysis
150.

Bin card is used in__________________?

A. administrative wing
B. workshop
C. foundry shop
D. stores
E. assembly shop
Answer» E. assembly shop