51.

The linear programming techniques can be applied successfully to industries like_________________?

A. iron and steel
B. food processing
C. oil and chemical
D. banking
E. all of the above
Answer» F.
52.

The important file in making a PERT is__________________?

A. an event can’t be accomplished until activities leading to it are completed
B. no activity from any event can be started from preceding event till it is completed
C. length of arrow has nothing to do with time
D. every activity must be completed before end point is reached
E. all of the above
Answer» F.
53.

The grouping of activities into organisational units is called_________________?

A. corporate plans
B. higher level management
C. functional authority
D. departmentatidn
E. company policy
Answer» E. company policy
54.

The first method invented for planning projects was________________?

A. bar chart method
B. milestone chart
C. critical path method (CPM)
D. programme evaluation and review technique (PERT)
E. none of the above
Answer» B. milestone chart
55.

The employees provident fund act is applicable to________________?

A. all industries
B. all industries other than small and medium industries
C. volunteers
D. the industries notified by Government
E. all major industries
Answer» E. all major industries
56.

The disadvantage of product layout is_________________?

A. high initial investment for the specialized facilities
B. skilled labour to operate machines
C. production time is longer, requiring more goods in inventory
D. high cost of inspection
E. costly and complex production control
Answer» B. skilled labour to operate machines
57.

The difference between the time available to do the job and the time required to do the job, is known as_________________?

A. event
B. float
C. duration
D. constraint
E. none of the above
Answer» C. duration
58.

The deductions for, employees provident fund start________________?

A. immediately on joining the service
B. after 60 days of joining the service
C. after 100 days of joining the service
D. after 240 days of joining the service
E. after one year of joining the service
Answer» E. after one year of joining the service
59.

The critical path of a network represents_______________________?

A. the minimum time required for completion of project
B. the maximum time required for completion of project
C. maximum cost required for completion of project
D. minimum cost required for completion of project
E. none of the above
Answer» B. the maximum time required for completion of project
60.

The critical activity has____________________?

A. maximum float
B. minimum float
C. zero float
D. average float
E. none of these
Answer» D. average float
61.

The basic difference between PERT and CPM is that_____________?

A. PERT deals with events and CPM with activities
B. critical path is determined in PERT only
C. costs are considered on CPM only and not in PERT
D. guessed times are used in PERT and evaluated times in CPM
E. PERT is used in workshops and CPM in plants
Answer» E. PERT is used in workshops and CPM in plants
62.

The assumption in PERT is__________________?

A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed
E. commissioning time can be changed, if activities are behind schedule
Answer» D. activities are fixed and can’t be changed
63.

The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?

A. event
B. free float
C. artificial
D. constraint
E. dummy
Answer» F.
64.

The appellate authority for an industrial dispute is________________?

A. management
B. labour court
C. high court/supreme court
D. board of directors
E. president
Answer» D. board of directors
65.

The amount deducted from the salary of workers towards employees provident fund is_______________?

A. credited into reserves of company
B. deposited in nationalised bank
C. deposited in post office
D. deposited in the account of worker with employer or Reserve Bank of India
E. deposited in the account of worker with Provident Fund Commissioner
Answer» F.
66.

The allowed time for a job equals standard time plus___________________?

A. policy allowance
B. interference allowance
C. process allowance
D. learning allowance
E. unforeseen allowance
Answer» B. interference allowance
67.

Scheduling gives information about____________________?

A. when work should start and how much work should be completed during a certain period
B. when work should complete
C. that how idle time can be minimized
D. proper utilisation of machines
E. none of the above
Answer» B. when work should complete
68.

Routing prescribes the_________________?

A. flow of material in the plant
B. proper utilization of man power
C. proper utilization of machines
D. inspection of final product
E. none of the above
Answer» B. proper utilization of man power
69.

Routing is essential in the following type of industry_________________?

A. assembly industry
B. process industry
C. job order industry
D. mass production industry
E. steel industry
Answer» B. process industry
70.

Routing assists engineers in deciding in advance___________________?

A. the flow of material in the plant
B. the methods of proper utilization of manpower
C. the methods of proper utilization of machines
D. the layout of factory facilities
E. normal route of workers through the plant
Answer» D. the layout of factory facilities
71.

Replacement studies are made on the fol-lowing basis_________________?

A. annual cost method
B. rate of return method
C. total life average method
D. present worth method
E. any one of the above
Answer» F.
72.

Queuing theory deals with problems of________________?

A. material handling
B. reducing the waiting time or idle Jajme
C. better utilization of man services
D. effective use of machines
E. none of the above
Answer» C. better utilization of man services
73.

Queuing theory is used for____________________?

A. inventory problems
B. traffic congestion studies
C. job-shop scheduling
D. all of the above
E. none of the above
Answer» E. none of the above
74.

Queuing theory is associated with __________________?

A. sales
B. inspection time
C. waiting time
D. production time
E. inventory
Answer» D. production time
75.

Product layout is employed for____________________?

A. batch production
B. continuous production
C. effective utilization of machine
D. all of the above
E. none of the above
Answer» C. effective utilization of machine
76.

Process layout is employed for_________________?

A. batch production
B. continuous type of product
C. effective utilisation of machines
D. all of the above
E. none of the above
Answer» B. continuous type of product
77.

Positive slack on a PERT indicates that project is________________?

A. ahead of schedule
B. beyond schedule
C. as per schedule
D. on critical path
E. none of the above
Answer» B. beyond schedule
78.

PMTP (predetermined motion time systems) include___________________?

A. MTM (method time measurement)
B. WFS (work factor systems)
C. BNTS (basic motion time study)
D. all of the above
E. none of the above
Answer» E. none of the above
79.

Pick up the incorrect statement about advantages of work sampling_________________?

A. permits a fine breakdown of activities and delays
B. simultaneous study of many operators may be made by a single observer
C. calculations are easier, method is economical and less time consuming
D. no time measuring devices are generally needed
E. as operators are not watched for long periods, chances of obtaining misleading results are less
Answer» B. simultaneous study of many operators may be made by a single observer
80.

Pick up the incorrect statement from the following. A critical ratio scheduling____________________?

A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of the above
Answer» F.
81.

Pick up the correct step used for scheduling a project by C.P.M.__________________?

A. a project is divided into various activities
B. required time for each activity is established
C. sequence of various activities is made according to their importance
D. network is drawn by connecting the activities and the events
E. all of the above
Answer» F.
82.

Pick up the correct statement about relationship between various floats______________________?

A. free float = total float
B. independent float = total float
C. independent float > free float
D. free float > total float
E. independent float < free float
Answer» F.
83.

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?

A. consumes time, but no resources
B. consumes resources but no time
C. consumes neither time nor resources
D. is a dangling event
E. consumes both resources and time
Answer» D. is a dangling event
84.

Pessimistic time is___________________?

A. the maximum time which an activity might require
B. the average time required for a job
C. the most probable time considering all conditions
D. the minimum time in which an activity can possibly be accomplished
E. the earliest finish
Answer» B. the average time required for a job
85.

PERT/CPM, techniques can be used for following applications____________________?

A. once through project
B. maintenance jobs
C. research and development
D. all non-technical jobs
E. all of the above
Answer» F.
86.

PERT stands for k (fit) project evaluation and review technique__________________?

A. project examination and review technique
B. project evaluation and reporting technique
C. process execution and reporting technology
D. project execution and results technique
Answer» B. project evaluation and reporting technique
87.

PERT is___________________?

A. an analytic tool in concept
B. limit up of event oriented diagrams
C. used for research and development projects
D. based on three time estimates for activities linking up two events
E. all of the above
Answer» F.
88.

PERT is the__________________?

A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique
Answer» C. activity oriented technique
89.

PERT and CPM are__________________?

A. techniques to determine project status
B. decision making techniques
C. charts which increase aesthetic appearance of rooms
D. aids to determine cost implications of project
E. aids to the decision maker
Answer» F.
90.

PERT has following time estimate_________________?

A. one time estimate
B. two time estimate
C. three time estimate
D. four time estimate
E. nil time estimate
Answer» D. four time estimate
91.

PERT analysis is based on____________________?

A. optimistic time
B. pessimistic time
C. most likely time
D. all of the above
E. none of the above
Answer» E. none of the above
92.

Per cent idle time for men or machines is found by___________________?

A. work sampling
B. time study
C. method study
D. work study
E. ABC analysis
Answer» B. time study
93.

One time measurement unit (TMU) in method time measurement system equals______________?

A. 0.0001 minute
B. 0.0006 minute
C. 0.006 minute
D. 0.001 minute
E. 0.06 minute
Answer» C. 0.006 minute
94.

One of the basic essentials of an incentive plan is that_________________?

A. a differential piece rate system should exist
B. minimum wages should be guaranteed
C. provide incentive to group efficiency performance
D. all standards should be based on optimum standards of production
E. all standards should be based on time studies
Answer» F.
95.

O on a PERT/CPM chart represents____________________?

A. an ordinary event
B. a significant event representing some mile-stone
C. an event to be transferred to other network chart
D. dangling event
E. dummy event
Answer» B. a significant event representing some mile-stone
96.

Motion study involves analysis of________________?

A. actions of operator
B. layout of work place
C. tooling and equipment
D. all of the above
E. none of the above
Answer» B. layout of work place
97.

Motion study is used for________________?_x005F_x000D_Choose the wrong statement?

A. improving a work method
B. improvising a work method
C. designing a work method
D. providing a schematic framework
E. reducing inventory costs
Answer» F.
98.

Monte Carlo solutions in queuing theory are extremely useful in queuing problems_________________?

A. that can’t be analysed mathematically
B. involving multistage queuing
C. to verify mathematical results
D. all of the above
E. none of the above
Answer» B. involving multistage queuing
99.

Military organisation is known as_______________________?

A. line organisation
B. line and staff organisation
C. functional organisation
D. all of the above
E. none of the above
Answer» B. line and staff organisation
100.

Micromotion study is__________________?

A. enlarged view of motion study
B. analysis of one stage of motion study
C. minute and detailed motion study
D. subdivision of an operation into therbligs and their analysis
E. motion study of small components upto mirco-seconds
Answer» E. motion study of small components upto mirco-seconds