Explore topic-wise MCQs in Mechanical Engineering.

This section includes 17 Mcqs, each offering curated multiple-choice questions to sharpen your Mechanical Engineering knowledge and support exam preparation. Choose a topic below to get started.

1.

For a classical (Wilson) model of determining economic order quantity (EOQ), the carrying and ordering costs are Cr and Co, respectively. For an annual demand D, the minimum yearly total inventory cost is

A. \(\sqrt{DC_0C_r}\)
B. \(\sqrt{1.5DC_0C_r}\)
C. \(\sqrt{2DC_0C_r}\)
D. \(\sqrt{3DC_0C_r}\)
Answer» D. \(\sqrt{3DC_0C_r}\)
2.

Actual observed time for an operation time was 1 min/piece. If the performance rating of the operator was 120 and a 5% personal time is to be provided, the standard time in min/piece is

A. 1
B. 1.2
C. 1.25
D. 1.26
Answer» E.
3.

Among the effects of design specifications on costs, which one of the following is the most significant that influences the producibility of end product?

A. Standard size
B. Large tolerance
C. Breakeven point
D. Cost estimate
Answer» C. Breakeven point
4.

In an MRP system, component demand is:

A. forecasted
B. established by the master production schedule
C. calculated by the MRP system from the master production schedule
D. ignored
Answer» D. ignored
5.

Assignment of work to manpower and machinery is known as

A. scheduling
B. loading
C. reporting
D. none of these
Answer» C. reporting
6.

A component can be produced by any of the four processes I, II, III and IV. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of 100 pieces isProcessFixed cost (in Rs.)Variable cost per piece (in Rs.)I203II501III402IV104

A. I
B. II
C. III
D. IV
Answer» C. III
7.

Life reliability of product is decided by

A. Quality assurance
B. Quality of design
C. Quality of manufacture
D. Quality of performance
Answer» E.
8.

All of the following are considered non-productive activities relating to equipment excepts

A. setting up or breaking down a machine
B. maintaining the machine
C. waiting for workers or material
D. all of the above are non-productive activities
Answer» E.
9.

In order to indicate the sequence of events and movements of men, material, etc., while work is being accomplished, the recording technique used is :

A. Flow diagram
B. Flow process chart
C. Gang process chart
D. Two handed process chart
Answer» B. Flow process chart
10.

A factory produces m (i = 1, 2, ..., m) products, each of which requires processing on n (j = 1, 2, ..., n) workstations. Let aij be the amount of processing time that one unit of the ith product requires on the jth workstation. Let the revenue from selling one unit of the ith product be ri and hi be the holding cost per unit per time period for the ith product. The planning horizon consists of T (t = 1, 2,..., T) time periods. The minimum demand that must be satisfied in time period t is dit, and the capacity of the jth workstation in time period t is cjt. Consider the aggregate planning formulation below, with decision variables Sit (amount of product i sold in time period t), Xit (amount of product i manufactured in time period t) and Iit (amount of product i held in inventory at the end of time period t).\({\rm{max}}\mathop \sum \limits_{t = 1}^T \mathop \sum \limits_{i = 1}^m \left( {{r_i}{S_{it}} - {h_i}{I_{it}}} \right)\)Subject toSit ≥ dit ∀ i, t< capacity constraint >< inventory balance constraint >Xit, Sit, Iit ≥ 0; Ii0 = 0The capacity constraints and inventory balance constraints for this formulation respectively are

A. \(\displaystyle\sum_i^m a_{ij}X_{it} \le c_{jt} \ \forall \ i, t\) and \(I_{it} = I_{i, t-1} + X_{it} - d_{it} \ \forall \ i, t\)
B. \(\displaystyle\sum_i^m a_{ij}X_{it} \le d_{it} \ \forall \ i, t\) and \(I_{it} = I_{i, t-1} + X_{it} - S_{it} \ \forall \ i, t\)
C. \(\displaystyle\sum_i^m a_{ij}X_{it} \le d_{it} \ \forall \ i, t\) and \(I_{it} = I_{i, t-1} + S_{it}- X_{it} \ \forall \ i, t\)
D. \(\displaystyle\sum_i^m a_{ij}X_{it} \le c_{jt} \ \forall \ j, t\) and \(I_{it} = I_{i, t - 1} + X_{it} - S_{it} \ \forall \ i, t\)
Answer» E.
11.

Pre-planning stage in production planning and control includes which of the following activities?

A. Inventory control
B. Quality control
C. Demand forecasting
D. Dispatching
Answer» D. Dispatching
12.

Job design means assigning the following tasks of a job to be performed by a worker in his daily routine:I. Job enlargement is the horizontal loading of workers jobII. Job rotation is interchanging amongst workers after a suitable interval of time.III. Job enrichment means giving additional responsibilities to workers who are more dignified.Which of the statements given above are correct?

A. I and II only
B. II and III only
C. I and III only
D. I, II and III
Answer» E.
13.

In the Method study, the symbol is used for:

A. Operation
B. Transportation
C. Delay
D. Storage
Answer» C. Delay
14.

In case of batch production the preferred layout will be

A. Process layout
B. Product layout
C. Combination type layout
D. Fixed type layout
Answer» B. Product layout
15.

In computing Wilson’s economic lot size for an item, by mistake, the demand rate estimate used was 40% higher than the true demand rate. Due to this error in the lot size computation, the total cost of set-ups plus inventory holding per unit time would rise above the true optimum by approximately

A. 1.4%
B. 6.3%
C. 18.3%
D. 8.7%
Answer» D. 8.7%
16.

Match the following:P) Process layouti) ship building, aircrafts manufactureQ) Product layoutii) for different types and different sizes of itemsR) Fixed position layoutiii) large varietyS) Combination layoutiv) large quantity

A. P-ii, Q-iii, R-iv, S-i
B. P-iv, Q-iii, R-i, S-ii
C. P-iii, Q-iv, R-i, S-ii
D. P-iv, Q-iii, R-ii, S-i
Answer» D. P-iv, Q-iii, R-ii, S-i
17.

A process layout is generally suggested for

A. Jobbing work
B. Batch production
C. Planned production
D. Discontinuous production
Answer» C. Planned production