 
			 
			MCQOPTIONS
 Saved Bookmarks
				This section includes 26 Mcqs, each offering curated multiple-choice questions to sharpen your Prestressed Concrete Structures knowledge and support exam preparation. Choose a topic below to get started.
| 1. | Calculate spacing of a prestressed concrete T slab using 12mm diameter of two legged stirrups such that fc is 415, vcw = 1900kn, balance shear is 934×103? | 
| A. | 165kn | 
| B. | 345kn | 
| C. | 230kn | 
| D. | 450kn | 
| Answer» B. 345kn | |
| 2. | Calculate the slope angle such that eccentricity is 750, length is 40m and stress induced is 1000n/m2? | 
| A. | 0.89 | 
| B. | 0.075 | 
| C. | 0.054 | 
| D. | 0.065 | 
| Answer» C. 0.054 | |
| 3. | Check for ultimate shear strength such that shear force, Vu = 2834 kn, According to IRC: 18-2000, the ultimate shear resistance of the support section uncracked in flexure loss ratio is 0.8, p is 12000×103, area is 0.88 x 106mm2? | 
| A. | 11.3n/mm2 | 
| B. | 23.5n/mm2 | 
| C. | 19.9n/mm2 | 
| D. | 10.9n/mm2 | 
| Answer» E. | |
| 4. | Calculate failure by crushing of concrete such that bw is 200, d is 1750, fck is 60n/mm2, b is800, Df is 400? | 
| A. | 12253x106nmm | 
| B. | 15253x106nmm | 
| C. | 18253x106nmm | 
| D. | 16253x106nmm | 
| Answer» D. 16253x106nmm | |
| 5. | Calculate the mid support section given that Ap = 7980mm2, fck = 60n/mm2, b = 800mm, fp = 1862n/mm2, bw = 200mm, Mu(required) = 16865knm, Dt = 400mm, d = 1750mm, failure by yielding of steel? | 
| A. | 1204 | 
| B. | 23402 | 
| C. | 1298 | 
| D. | = 16865knm, Dt = 400mm, d = 1750mm, failure by yielding of steel?a) 1204b) 23402c) 1298d) 45367 | 
| Answer» C. 1298 | |
| 6. | Calculate effective length of Road on a highway given the overall thickness is 500mm and thickness of wearing coarse is 80mm (x is 3.6m)? | 
| A. | 4.76m | 
| B. | 34.8m | 
| C. | 2.34m | 
| D. | 1.45m | 
| Answer» B. 34.8m | |
| 7. | Calculate bending moment of dead load given total load = 14n/mm2, Dead load bending moment dead weight of slab = 12kn/m2, dead weight of w.c = 1.76kn/m2, span length is 10.4m? | 
| A. | 120knm | 
| B. | 130knm | 
| C. | 190knm | 
| D. | 160knm | 
| Answer» D. 160knm | |
| 8. | Calculate Permissible stresses compressive stresses in concrete at transfer and working loads, as recommended given fct = 15n/mm2, fst = 0.8, fcw is 12n/mm2? | 
| A. | 13.2 | 
| B. | 13.4 | 
| C. | 13.8 | 
| D. | 13.0 | 
| Answer» B. 13.4 | |
| 9. | Long span continuous prestressed concrete bridges are built of which type of box girders? | 
| A. | Single celled | 
| B. | 3 celled | 
| C. | Multi celled | 
| D. | 4 celled | 
| Answer» D. 4 celled | |
| 10. | In India, a large number of long span bridges have been constructed using __________ | 
| A. | Simply supported beam | 
| B. | UDL | 
| C. | Point | 
| D. | Cantilever | 
| Answer» E. | |
| 11. | The post tensioning is ideally suited for prestressing of __________ | 
| A. | Short span girders | 
| B. | Long span girders | 
| C. | Effective span | 
| D. | Limited span | 
| Answer» C. Effective span | |
| 12. | The precast prestressed I and inverted T beams have been standardized by __________ | 
| A. | Pulverization association | 
| B. | Cement and concrete association | 
| C. | Brick association | 
| D. | Steel association | 
| Answer» C. Brick association | |
| 13. | The prestressed concrete bridge decks generally comprise __________ | 
| A. | Precast pretensioned | 
| B. | Precast post tensioned | 
| C. | Partially pretensioned | 
| D. | Partially post tensioned | 
| Answer» B. Precast post tensioned | |
| 14. | CALCULATE_FAILURE_BY_CRUSHING_OF_CONCRETE_SUCH_THAT_BW_IS_200,_D_IS_1750,_FCK_IS_60N/MM2,_B_IS800,_DF_IS_400??$ | 
| A. | 12253x106nmm | 
| B. | 15253x106nmm | 
| C. | 18253x106nmm | 
| D. | 16253x106nmm | 
| Answer» D. 16253x106nmm | |
| 15. | CALCULATE_THE_MID_SUPPORT_SECTION_GIVEN_THAT_AP_=_7980MM2,_FCK_=_60N/MM2,_B_=_800MM,_FP_=_1862N/MM2,_BW_=_200MM,_MU(REQUIRED)_=_16865KNM,_DT_=_400MM,_D_=_1750MM,_FAILURE_BY_YIELDING_OF_STEEL??$ | 
| A. | 1204 | 
| B. | 23402 | 
| C. | 1298 | 
| D. | 45367 | 
| Answer» C. 1298 | |
| 16. | Calculate the slope angle such that eccentricity is 750, length is 40m and stress induced is 1000n/m2?$ | 
| A. | 0.89 | 
| B. | 0.075 | 
| C. | 0.054 | 
| D. | 0.065 | 
| Answer» C. 0.054 | |
| 17. | Check for ultimate shear strength such that shear force, Vu = 2834 kn, According to IRC: 18-2000, the ultimate shear resistance of the support section uncracked in flexure loss ratio is 0.8, p is 12000√ó103, area is 0.88 x 106mm2?$# | 
| A. | 11.3n/mm<sup>2</sup> | 
| B. | 23.5n/mm<sup>2</sup> | 
| C. | 19.9n/mm<sup>2</sup> | 
| D. | 10.9n/mm<sup>2</sup> | 
| Answer» E. | |
| 18. | Calculate spacing of a prestressed concrete T slab using 12mm diameter of two legged stirrups such that fc is 415, vcw = 1900kn, balance shear is 934√ó103?$ | 
| A. | 165kn | 
| B. | 345kn | 
| C. | 230kn | 
| D. | 450kn | 
| Answer» B. 345kn | |
| 19. | Calculate effective length of Road on a highway given the overall thickness is 500mm and thickness of wearing coarse is 80mm ( x is 3.6m)? | 
| A. | 4.76m | 
| B. | 34.8m | 
| C. | 2.34m | 
| D. | 1.45m | 
| Answer» B. 34.8m | |
| 20. | Calculate bending moment of dead load given total load = 14n/mm2, Dead load bending moment dead weight of slab = 12kn/m2, dead weight of w.c = 1.76kn/m2, span length is 10.4m? | 
| A. | 120knm | 
| B. | 130knm | 
| C. | 190knm | 
| D. | 160knm | 
| Answer» D. 160knm | |
| 21. | Calculate Permissible stresses compressive stresses in concrete at transfer and working loads, as recommended given fct = 15n/mm2, fst = 0.8, fcw is 12n/mm2? | 
| A. | 13.2 | 
| B. | 13.4 | 
| C. | 13.8 | 
| D. | 13.0 | 
| Answer» B. 13.4 | |
| 22. | Long span continuous prestressed concrete bridges are built of which type of box girders: | 
| A. | Single celled | 
| B. | 3 celled | 
| C. | Multi celled | 
| D. | 4 celled | 
| Answer» D. 4 celled | |
| 23. | In India, a large number of long span bridges have been constructed using: | 
| A. | Simply supported beam | 
| B. | UDL | 
| C. | Point | 
| D. | Cantilever | 
| Answer» E. | |
| 24. | The post tensioning is ideally suited for prestressing of: | 
| A. | Short span girders | 
| B. | Long span girders | 
| C. | Effective span | 
| D. | Limited span | 
| Answer» B. Long span girders | |
| 25. | The precast prestressed I and inverted T beams have been standardized by: | 
| A. | Pulverization association | 
| B. | Cement and concrete association | 
| C. | Brick association | 
| D. | Steel association | 
| Answer» C. Brick association | |
| 26. | The prestressed concrete bridge decks generally comprise | 
| A. | Precast pretensioned | 
| B. | Precast post tensioned | 
| C. | Partially pretensioned | 
| D. | Partially post tensioned | 
| Answer» B. Precast post tensioned | |