1.

After proportioning, the plasticity index of the mix was found to be 7%. For what course can the mix be used for?

A. Base
B. Subbase
C. Subgrade
D. Surface
Answer» E.
2.

The triangular method used for proportioning of aggregates is a type of ______ method.

A. Analytical
B. Graphical
C. Trial and error
D. Sieve analysis
Answer» C. Trial and error
3.

Mechanical stabilization of soil can be used in the surface course.

A. True
B. False
Answer» B. False
4.

The field control tests are conducted for which of the below properties?

A. Density and stability
B. Moisture content, stability and density
C. Moisture content and stability
D. Density and Moisture content
Answer» E.
5.

The distribution curves of three materials A, B and C are plotted and their balancing lines are also obtained. According to Rothfutch s method, ______ ends of balancing lines of ______ and ______ are to be connected.

A. Same, A&B, B&C
B. Opposite, A&B, B&C
C. Same, A&C, B&C
D. Opposite, A&C, B&C
Answer» C. Same, A&C, B&C
6.

The portioning of soil aggregate mixture is done so as to attain ______

A. Minimum dry density
B. Minimum bulk density
C. Maximum dry density
D. Maximum bulk density
Answer» D. Maximum bulk density
7.

The advent of computers has made the analytical method more popular.

A. True
B. False
Answer» B. False
8.

What is the limit of liquid limit for a base course to be constructed using mechanical soil stabilization?

A. Maximum 35%
B. Minimum 35%
C. Maximum 25%
D. Minimum 25%
Answer» D. Minimum 25%
9.

The method of Vibro compaction is generally used for which soil type?

A. Loose soil
B. Compacted soil
C. Clayey soil
D. Semi-compacted soil
Answer» B. Compacted soil
10.

What is the capacity that a pavement constructed in a light rainfall area using Mehra s method can carry?

A. 50 tonnes of mixed traffic per year
B. 200 tonnes of mixed traffic per year
C. 50 tonnes of mixed traffic per day
D. 200 tonnes of missed traffic per day
Answer» D. 200 tonnes of missed traffic per day