 
			 
			MCQOPTIONS
 Saved Bookmarks
				This section includes 162 Mcqs, each offering curated multiple-choice questions to sharpen your Automobile Engineering knowledge and support exam preparation. Choose a topic below to get started.
| 1. | According to Muther, the basic principle of best layout is | 
| A. | principle of over-all integration | 
| B. | principle of flow | 
| C. | principle of flexibility | 
| D. | all of these | 
| Answer» E. | |
| 2. | In a functional organisation | 
| A. | quality of work is better | 
| B. | wastage of material is minimum | 
| C. | specialised knowledge and guidance to individual worker is provided | 
| D. | all of the above | 
| Answer» E. | |
| 3. | Which of the following are the principles of material handling? | 
| A. | keep all the handling to the minimum | 
| B. | select only efficient handling equipment | 
| C. | move the heaviest weight to the least distance | 
| D. | all of the above | 
| Answer» E. | |
| 4. | A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is | 
| A. | 0.50 | 
| B. | 0.66 | 
| C. | 0.84 | 
| D. | 0.95 | 
| Answer» D. 0.95 | |
| 5. | For material transportation, conveyors are used when the prevailing conditions include | 
| A. | loads are uniform | 
| B. | routes do not vary | 
| C. | materials move relatively continuously | 
| D. | all of these | 
| Answer» E. | |
| 6. | When slack of an activity is positive | 
| A. | it represents a situation where extra resources are available and the completion of project is not delayed | 
| B. | it represents that a programme falls behind schedule and additional resources are required to complete the project in time | 
| C. | the activity is critical and any delay in its performance will delay the completion of whole project | 
| D. | any one of the above | 
| Answer» E. | |
| 7. | Break even point is the point where | 
| A. | fixed and variable cost lines intersect | 
| B. | fixed and total cost lines intersect | 
| C. | variable and total cost lines intersect | 
| D. | sales revenue and total expensive lines intersect | 
| Answer» E. | |
| 8. | The bonus increases in proportion to the increase in efficiency. This statement applies to | 
| A. | Halsey plan | 
| B. | Ganttplan | 
| C. | Emerson's efficiency plan | 
| D. | Rowan plan | 
| Answer» D. Rowan plan | |
| 9. | M.T.M. is used to | 
| A. | improve existing methods | 
| B. | establish time standards | 
| C. | develop effective methods in advance of the beginning of production | 
| D. | all of the above | 
| Answer» E. | |
| 10. | F. W. Taylor introduced a system of organisation known as | 
| A. | line organisation | 
| B. | functional organisation | 
| C. | line and staff organisation | 
| D. | line, staff and functional organisation | 
| Answer» C. line and staff organisation | |
| 11. | The unit cost in case of batch production is __________ as compared to jobbing production. | 
| A. | same | 
| B. | low | 
| C. | high | 
| D. | None of these | 
| Answer» C. high | |
| 12. | A feasible solution to the linear programming problem should | 
| A. | satisfy the problem constraints | 
| B. | optimise the objective function | 
| C. | satisfy the problem constraints and non-negativity restrictions | 
| D. | satisfy the non-negativity restrictions | 
| Answer» D. satisfy the non-negativity restrictions | |
| 13. | CPM stands for | 
| A. | Combined Process Method | 
| B. | Critical Path Method | 
| C. | Common Planning Method | 
| D. | Critical Process Method | 
| Answer» C. Common Planning Method | |
| 14. | Slack may be positive, zero or negative. | 
| A. | Agree | 
| B. | Disagree | 
| C. | Can't say | 
| D. | None of these | 
| Answer» B. Disagree | |
| 15. | Service time in queuing theory is usually assumed to follow | 
| A. | normal distribution | 
| B. | Poissons distribution | 
| C. | Erlang distribution | 
| D. | exponential law | 
| Answer» E. | |
| 16. | In a thermal power plant, coal from the coal handling plant is moved to the boiler bunker through a | 
| A. | belt conveyor | 
| B. | bucket conveyor | 
| C. | fork lift truck | 
| D. | overhead crane | 
| Answer» B. bucket conveyor | |
| 17. | The product layout | 
| A. | lowers overall manufacturing time | 
| B. | requires less space for placing machines | 
| C. | utilises machine and labour better | 
| D. | all of these | 
| Answer» E. | |
| 18. | Linear programming can be applied successfully to | 
| A. | chemical industry | 
| B. | oil industry | 
| C. | banks | 
| D. | all of these | 
| Answer» E. | |
| 19. | Process layout is employed | 
| A. | where low volume of production is required | 
| B. | where similar jobs are manufactured on similar machines | 
| C. | where machines are arranged on functional basis | 
| D. | all of the above | 
| Answer» E. | |
| 20. | The factors which are to be considered while developing a good wage incentive plan will include | 
| A. | adequate incentive | 
| B. | ease of administration | 
| C. | guaranteed basic pay | 
| D. | all of these | 
| Answer» E. | |
| 21. | Micromotion study is | 
| A. | analysis of one stage of motion chart | 
| B. | motion study, when seen on a time chart | 
| C. | subdivision of an operation into therbligs and their analysis | 
| D. | enlarged view of motion study | 
| Answer» D. enlarged view of motion study | |
| 22. | PERT is a project planning and control technique. | 
| A. | Yes | 
| B. | No | 
| C. | Can't say | 
| D. | None of these | 
| Answer» B. No | |
| 23. | In perpetual inventory control, the material is checked as it reaches its | 
| A. | maximum value | 
| B. | minimum value | 
| C. | average value | 
| D. | any one of these | 
| Answer» E. | |
| 24. | An activity of the project is graphically represented by __________ on the network diagram. | 
| A. | a circle | 
| B. | a straight line | 
| C. | an arrow | 
| D. | None of these | 
| Answer» D. None of these | |
| 25. | A dummy activity in a net work diagram | 
| A. | is represented by a dotted line | 
| B. | is an artificial activity | 
| C. | does not consume time or resources | 
| D. | all of these | 
| Answer» E. | |
| 26. | Earliest finish time can be regarded as | 
| A. | earliest start time + duration of activity | 
| B. | earliest start time - duration of activity | 
| C. | latest finish time + duration of activity | 
| D. | latest finish time - duration of activity | 
| Answer» B. earliest start time - duration of activity | |
| 27. | In inventory control, the economic ordering quantity is obtained by the quantity whose procurement cost is equal to inventory carrying cost. | 
| A. | True | 
| B. | False | 
| C. | Can't say | 
| D. | None of these | 
| Answer» B. False | |
| 28. | Standard time is equal to | 
| A. | normal time minus allowances | 
| B. | normal time plus allowances | 
| C. | representative time multiplied by rating factor | 
| D. | normal time taken by an operation | 
| Answer» C. representative time multiplied by rating factor | |
| 29. | CPM requires | 
| A. | single time estimate | 
| B. | double time estimate | 
| C. | triple time estimate | 
| D. | none of these | 
| Answer» B. double time estimate | |
| 30. | Merit rating is the method of determining the | 
| A. | relative values of a job | 
| B. | worker's performance on a job | 
| C. | worth of a machine | 
| D. | value of overall production | 
| Answer» C. worth of a machine | |
| 31. | In time study, normal time is more than the standard time. | 
| A. | Yes | 
| B. | No | 
| C. | Can't say | 
| D. | None of these | 
| Answer» C. Can't say | |
| 32. | Which of the following conditions are necessary for applying linear programming? | 
| A. | These must be a well defined objective function. | 
| B. | The decision variables should be interrelated and non-negative. | 
| C. | The resources must be in limited supply. | 
| D. | all of the above | 
| Answer» E. | |
| 33. | The type of layout used for manufacturing steam turbines, is | 
| A. | product layout | 
| B. | process layout | 
| C. | fixed position layout | 
| D. | any one of these | 
| Answer» D. any one of these | |
| 34. | Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is __________ the standard time. | 
| A. | one-fourth | 
| B. | one-half | 
| C. | equal to | 
| D. | twice | 
| Answer» C. equal to | |
| 35. | If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then break even point is equal to | 
| A. | (F × V)/P | 
| B. | (F × P)/V | 
| C. | F/[1 + (V/P)] | 
| D. | F/[1 - (V/P)] | 
| Answer» E. | |
| 36. | The value engineering technique in which experts of the same rank assemble for product development is called | 
| A. | Delphi | 
| B. | brain storming | 
| C. | morphological analysis | 
| D. | direct expert comparison | 
| Answer» C. morphological analysis | |
| 37. | A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT). | 
| A. | Correct | 
| B. | Incorrect | 
| C. | Can't say | 
| D. | None of these | 
| Answer» B. Incorrect | |
| 38. | For handling materials during manufacture of cement, a __________ is widely used. | 
| A. | belt conveyor | 
| B. | bucket conveyor | 
| C. | fork lift truck | 
| D. | overhead crane | 
| Answer» C. fork lift truck | |
| 39. | P.M.T.S. (Predetermined Motion Time Systems) include | 
| A. | M.T.M. (Method Time Measurement) | 
| B. | W.F.S. (Work Factor Systems) | 
| C. | B.M.T.S. (Basic Motion Time Study) | 
| D. | all of these | 
| Answer» E. | |
| 40. | Gantt chart gives information about | 
| A. | scheduling and routing | 
| B. | sales | 
| C. | production schedule | 
| D. | machine utilisation | 
| Answer» D. machine utilisation | |
| 41. | Break even analysis represents the relationship between cost and volume. | 
| A. | True | 
| B. | False | 
| C. | Can't say | 
| D. | None of these | 
| Answer» B. False | |
| 42. | The start or completion of task is called | 
| A. | an event | 
| B. | an activity | 
| C. | a duration | 
| D. | none of these | 
| Answer» B. an activity | |
| 43. | The type of organisation preferred for an automobile industry, is | 
| A. | line organisation | 
| B. | functional organisation | 
| C. | line and staff organisation | 
| D. | line, staff and functional organisation | 
| Answer» D. line, staff and functional organisation | |
| 44. | Actual performance of a task is called | 
| A. | an event | 
| B. | an activity | 
| C. | a duration | 
| D. | none of these | 
| Answer» C. a duration | |
| 45. | Dummy activities are used to | 
| A. | determine the critical path | 
| B. | determine the project completion time | 
| C. | maintain the required net work | 
| D. | none of these | 
| Answer» D. none of these | |
| 46. | Halsey plan of wage incentive | 
| A. | is not applied to all level of workers | 
| B. | is applied to all level of workers | 
| C. | does not guarantee minimum wage | 
| D. | is based upon efficiency of worker | 
| Answer» C. does not guarantee minimum wage | |
| 47. | The production cost per unit can be reduced by | 
| A. | producing more with increased inputs | 
| B. | producing more with the same inputs | 
| C. | eliminating idle time | 
| D. | minimising resource waste | 
| Answer» C. eliminating idle time | |
| 48. | Break even analysis is a | 
| A. | short term analysis | 
| B. | long term analysis | 
| C. | average of short and long term analysis | 
| D. | any one of these | 
| Answer» B. long term analysis | |
| 49. | In value engineering, important consideration is given to | 
| A. | customer satisfaction | 
| B. | function concept | 
| C. | profit maximisation | 
| D. | cost reduction | 
| Answer» E. | |
| 50. | In jobbing production | 
| A. | highly skilled workers are needed | 
| B. | unit costs are high | 
| C. | operations are labour-intensive | 
| D. | all of these | 
| Answer» E. | |