Explore topic-wise MCQs in Irrigation Engineering.

This section includes 9 Mcqs, each offering curated multiple-choice questions to sharpen your Irrigation Engineering knowledge and support exam preparation. Choose a topic below to get started.

1.

The foundation pressure used in the pressure grouting is equal to _________________

A. 2.0 D N/cm2
B. 2.5 D N/cm2
C. 5.0 D N/cm2
D. 3.0 D N/cm2
Answer» C. 5.0 D N/cm2
2.

Which of the following joints justifies the two-dimensional analysis of gravity dams?

A. Longitudinal joints
B. Transverse joints
C. Construction joints
D. Contraction joints
Answer» C. Construction joints
3.

The horizontal joints that extends through the entire width of the dam section and are developed at each lift height is called as ___________________

A. transverse joints
B. longitudinal joints
C. construction joints
D. contraction joints
Answer» C. construction joints
4.

The general value of lift for concrete is taken as __________________

A. 1.5 m
B. 2.5 m
C. 3 m
D. 4 m
Answer» B. 2.5 m
5.

In order to reduce uplift on a gravity dam, the type of grouting done is ____________________

A. curtain grouting near the heel
B. consolidation grouting near the heel
C. curtain grouting near the toe
D. consolidation grouting near the toe
Answer» B. consolidation grouting near the heel
6.

Leakage through the transverse joints in a gravity dam is prevented by ____________

A. shear keys
B. keyways
C. water stops
D. galleries
Answer» D. galleries
7.

Transverse joints in concrete gravity dams are the ___________________________

A. horizontal construction joints at each lift height
B. vertical construction joints of full height and width
C. diagonal construction joints for torsion
D. longitudinal construction joints of full width
Answer» C. diagonal construction joints for torsion
8.

Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?i. Providing drainage gallery to collect seepage waterii. Constructing cut-off under upstream faceiii. Pressure grouting in dam foundationiv. Provision of shear keys or keyways

A. i and ii
B. i, ii and iii
C. i, ii and iv
D. i, ii, iii and iv
Answer» C. i, ii and iv
9.

The provision of drainage gallery in a gravity dam helps in reducing ____________________

A. hydrostatic pressure
B. seepage pressure
C. silt pressure
D. both hydrostatic pressure and seepage pressure
Answer» C. silt pressure