1. |
Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?i. Providing drainage gallery to collect seepage waterii. Constructing cut-off under upstream faceiii. Pressure grouting in dam foundationiv. Provision of shear keys or keyways |
A. | i and ii |
B. | i, ii and iii |
C. | i, ii and iv |
D. | i, ii, iii and iv |
Answer» C. i, ii and iv | |