1.

Which of the following attempts are made to reduce the uplift in order to economize on the provided section of a concrete gravity dam?i. Providing drainage gallery to collect seepage waterii. Constructing cut-off under upstream faceiii. Pressure grouting in dam foundationiv. Provision of shear keys or keyways

A. i and ii
B. i, ii and iii
C. i, ii and iv
D. i, ii, iii and iv
Answer» C. i, ii and iv


Discussion

No Comment Found