Explore topic-wise MCQs in Industrial Engineering and Production Management.

This section includes 69 Mcqs, each offering curated multiple-choice questions to sharpen your Industrial Engineering and Production Management knowledge and support exam preparation. Choose a topic below to get started.

1.

Break-even analysis consists of

A. Fixed cost
B. Variable cost
C. Fixed and variable costs
D. Operation costs
Answer» D. Operation costs
2.

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle
B. A straight line
C. An arrow
D. None of these
Answer» D. None of these
3.

Pick up the correct statement about relationship between various floats

A. Free float = total float
B. Independent float = total float
C. Independent float > free float
D. Independent float < free float
Answer» E.
4.

PMTP (predetermined motion time systems) include

A. MTM (method time measurement)
B. WFS (work factor systems)
C. BNTS (basic motion time study)
D. All of the above
Answer» E.
5.

Routing assists engineers in deciding in advance

A. The flow of material in the plant
B. The methods of proper utilization of manpower
C. The methods of proper utilization of machines
D. The layout of factory facilities
Answer» D. The layout of factory facilities
6.

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system
B. A merit rating system
C. A job evaluation system
D. His individual performance
Answer» C. A job evaluation system
7.

The amount deducted from the salary of workers towards employee s provident fund is

A. Credited into reserves of company
B. Deposited in nationalized bank
C. Deposited in post office
D. Deposited in the account of worker with Provident Fund Commissioner
Answer» E.
8.

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system
B. Primary cost method
C. Current value method
D. Fixed price method
Answer» B. Primary cost method
9.

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view
B. Motion study observed on enhanced time intervals
C. Motion study of a sequence of operations conducted systematically
D. Study of man and machine conducted simultaneously
Answer» B. Motion study observed on enhanced time intervals
10.

Travel charts provide

A. An idea of the flow of materials at various stages
B. A compact estimate of the handling which must be done between various work sections
C. The information for changes required in rearranging material handling equipment
D. An approximate estimate of the handling which must be done at a particular station
Answer» C. The information for changes required in rearranging material handling equipment
11.

Positive slack on a PERT indicates that project is

A. Ahead of schedule
B. Beyond schedule
C. As per schedule
D. On critical path
Answer» B. Beyond schedule
12.

The performance of a specific task in CPM is known as

A. Dummy
B. Event
C. Activity
D. Contract
Answer» D. Contract
13.

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan
B. Taylor plan
C. Halsey premium plan
D. Gilbert plan
Answer» D. Gilbert plan
14.

For handling materials during manufacture of cement, a _________ is widely used.

A. Belt conveyor
B. Bucket conveyor
C. Fork lift truck
D. Overhead crane
Answer» C. Fork lift truck
15.

For ship vessel industry the following layout is best suited

A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer» D. Plant layout
16.

Standing orders which are statutory are applicable to

A. All industries
B. All process industries and thermal power plants
C. Only major industries
D. All industries employing more than 100 workers
Answer» E.
17.

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish
B. Early start
C. Late start
D. Late finish
Answer» B. Early start
18.

Replacement studies are made on the following basis

A. Annual cost method
B. Rate of return method
C. Total life average method
D. Any one of the above
Answer» E.
19.

'Value' for value engineering and analysis purposes is defined as

A. Purchase value
B. Saleable value
C. Depreciated value
D. Function/cost
Answer» E.
20.

Which of the following layouts is suited to job production?

A. Process layout
B. Product layout
C. Fixed position layout
D. Plant layout
Answer» B. Product layout
21.

The appellate authority for an industrial dispute is

A. Management
B. Labour court
C. High court/supreme court
D. Board of directors
Answer» D. Board of directors
22.

Breakeven analysis is a

A. Short term analysis
B. Long term analysis
C. Average of short and long term analysis
D. Any one of these
Answer» B. Long term analysis
23.

Expediting function consists in keeping a watch on

A. Operator's activity
B. Flow of material and in case of trouble locate source of trouble
C. Minimizing the delays
D. Making efficient dispatching
Answer» C. Minimizing the delays
24.

ABC analysis deals with

A. Analysis of process chart
B. Flow of material
C. Ordering schedule of job
D. Controlling inventory costs money
Answer» E.
25.

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over
B. Lowest competitive price
C. Various elements of the cost
D. All of the above
Answer» E.
26.

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources
B. Consumes resources but no time
C. Consumes neither time nor resources
D. Is a dangling event
Answer» D. Is a dangling event
27.

The probability distribution of activity times in PERT follows following distribution

A. Normal
B. Binomial
C. Beta
D. Exponential
Answer» D. Exponential
28.

CPM is the

A. Time oriented technique
B. Event oriented technique
C. Activity oriented technique
D. Target oriented technique
Answer» D. Target oriented technique
29.

The mathematical technique for finding the best use of limited resources in an optimum manner is known as

A. Operation research
B. Linear programming
C. Network analysis
D. Break-even analysis
Answer» C. Network analysis
30.

Gantt charts are used for

A. Forecasting sales
B. Production schedule
C. Scheduling and routing
D. Linear programming
Answer» C. Scheduling and routing
31.

Break-even analysis shows profit when

A. Sales revenue > total cost
B. Sales revenue = total cost
C. Sales revenue < total cost
D. Variable cost < fixed cost
Answer» B. Sales revenue = total cost
32.

Routing is essential in the following type of industry

A. Assembly industry
B. Process industry
C. Job order industry
D. Mass production industry
Answer» B. Process industry
33.

Merit Rating is the method of determining worth of

A. A job
B. An individual employee
C. A particular division in workshop
D. Machine
Answer» C. A particular division in workshop
34.

In break-even analysis, total cost consists of

A. Fixed cost
B. Variable cost
C. Fixed cost + variable cost
D. Fixed cost + variable cost + overheads
Answer» D. Fixed cost + variable cost + overheads
35.

Inventory control in production, planning and control aims at

A. Achieving optimization
B. Ensuring against market fluctuations
C. Acceptable customer service at low capital investment in inventory
D. Discounts allowed in bulk purchase
Answer» D. Discounts allowed in bulk purchase
36.

One of the basic essentials of an incentive plan is that

A. A differential piece rate system should exist
B. Minimum wages should be guaranteed
C. Provide incentive to group efficiency performance
D. All standards should be based on time studies
Answer» E.
37.

The break-even point represents

A. The most economical level of operation of any industry
B. The time when unit can run without i loss and profit
C. Time when industry will undergo loss
D. The time when company can make maximum profits
Answer» D. The time when company can make maximum profits
38.

The critical path of a network represents

A. The minimum time required for completion of project
B. The maximum time required for completion of project
C. Maximum cost required for completion of project
D. Minimum cost required for completion of project
Answer» B. The maximum time required for completion of project
39.

If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then break-even point is equal to

A. (F V)/P
B. (F P)/V
C. F/[1 + (V/P)]
D. F/[1 - (V/P)]
Answer» E.
40.

The disadvantage of product layout is

A. High initial investment for the specialized facilities
B. Skilled labour to operate machines
C. Production time is longer, requiring more goods in inventory
D. High cost of inspection
Answer» B. Skilled labour to operate machines
41.

Bin card is used in

A. Administrative wing
B. Workshop
C. Foundry shop
D. Stores
Answer» E.
42.

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth
B. One-half
C. Equal to
D. Twice
Answer» C. Equal to
43.

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan
B. Taylor Differential Piece rate system
C. Halsey Premium plan
D. Day work plan
Answer» D. Day work plan
44.

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organization
B. Line and staff organization
C. Functional organization
D. Effective organization
Answer» B. Line and staff organization
45.

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown
B. Early start and late finish of an activity are clearly marked
C. Activity times are clear
D. Interrelationship among activities is clearly shown
Answer» E.
46.

Break-even analysis can be used for

A. Short run analysis
B. Long run analysis
C. Average of above two run analysis
D. There is no such criterion
Answer» B. Long run analysis
47.

Value engineering aims at finding out the

A. Depreciation value of a product
B. Resale value of a product
C. Major function of the item and accomplishing the same at least cost without change in quality
D. Break-even point when machine requires change
Answer» D. Break-even point when machine requires change
48.

The simplex method is the basic method for

A. Value analysis
B. Operation research
C. Linear programming
D. Model analysis
Answer» D. Model analysis
49.

At the break-even point,

A. Total cost is more than the sales revenue
B. Total cost is less than the sales revenue
C. Total cost is equal to sales revenue
D. Fixed cost is equal to variable cost
Answer» D. Fixed cost is equal to variable cost
50.

PERT has following time estimate

A. One time estimate
B. Two time estimate
C. Three time estimate
D. Four time estimate
Answer» D. Four time estimate