Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it |
| A. | Consumes time, but no resources |
| B. | Consumes resources but no time |
| C. | Consumes neither time nor resources |
| D. | Is a dangling event |
| Answer» D. Is a dangling event | |