1. |
In which of the following contract; contractor is required to offer a fixed sum for job in all respect as per given drawings and details? |
A. | Item rate contract |
B. | Lump-sum contract |
C. | All in one contract |
D. | Labor contract |
Answer» C. All in one contract | |
2. |
The construction industry has accounted for about ............% of all deaths due to accident at place of work |
A. | 5 |
B. | 20 |
C. | 25 |
D. | 30 |
Answer» C. 25 | |
3. |
Full width of road should be taken for bituminous work at a time so that job is completed in time. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» C. none | |
4. |
Who should be allowed to go below slab when centering is in position and concreting of slab is going on |
A. | Only head carpenter |
B. | Every worker |
C. | Nobody |
D. | Only safety officer |
Answer» D. Only safety officer | |
5. |
Before starting piling work, a complete knowledge of underground structures (such as sewers, water pipeline, gas mains etc.) is essential. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» B. Disagree | |
6. |
If work of piling is to be carried out at night, minimum........... 'lux luminance lights should be used. |
A. | 60 |
B. | 200 |
C. | 150 |
D. | 100 |
Answer» E. | |
7. |
Economic cost is the only reason for which a contractor should be conscious of construction safety. |
A. | TRUE |
B. | FALSE |
C. | none |
D. | all |
Answer» C. none | |
8. |
The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» B. Disagree | |