1.

In which of the following contract; contractor is required to offer a fixed sum for job in all respect as per given drawings and details?

A. Item rate contract
B. Lump-sum contract
C. All in one contract
D. Labor contract
Answer» C. All in one contract
2.

The construction industry has accounted for about ............% of all deaths due to accident at place of work

A. 5
B. 20
C. 25
D. 30
Answer» C. 25
3.

Full width of road should be taken for bituminous work at a time so that job is completed in time.

A. Agree
B. Disagree
C. none
D. all
Answer» C. none
4.

Who should be allowed to go below slab when centering is in position and concreting of slab is going on

A. Only head carpenter
B. Every worker
C. Nobody
D. Only safety officer
Answer» D. Only safety officer
5.

Before starting piling work, a complete knowledge of underground structures (such as sewers, water pipeline, gas mains etc.) is essential.

A. Agree
B. Disagree
C. none
D. all
Answer» B. Disagree
6.

If work of piling is to be carried out at night, minimum........... 'lux luminance lights should be used.

A. 60
B. 200
C. 150
D. 100
Answer» E.
7.

Economic cost is the only reason for which a contractor should be conscious of construction safety.

A. TRUE
B. FALSE
C. none
D. all
Answer» C. none
8.

The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles.

A. Agree
B. Disagree
C. none
D. all
Answer» B. Disagree