1. |
In the construction procedure for bituminous carpet, what treatment is provided if the existing surface is made of soft aggregates? |
A. | Tack coat |
B. | Prime coat |
C. | Seal coat |
D. | Stabilization |
Answer» C. Seal coat | |
2. |
The full grout penetration macadam is used in which type of areas? |
A. | Low rainfall |
B. | Frost condition |
C. | Heavy rainfall |
D. | Hot condition |
Answer» D. Hot condition | |
3. |
Premix carpet can be classified as open-graded and dense-graded. |
A. | True |
B. | False |
Answer» C. | |
4. |
What is the specified thickness of asphaltic concrete? |
A. | 40 mm |
B. | 75 mm |
C. | 50 mm |
D. | 65 mm |
Answer» B. 75 mm | |
5. |
What type of construction does the below figure represent? |
A. | Mastic asphalt |
B. | Carpet |
C. | Built-up Grout |
D. | Penetration Macadam |
Answer» E. | |
6. |
The premix type of bituminous construction is carried out in the ______ |
A. | Travelling plant |
B. | Field |
C. | Mixing plant |
D. | Base |
Answer» C. Mixing plant | |
7. |
The use of bituminous surface dressing with precoated aggregates is used when ______ is required. |
A. | Poor adhesion |
B. | Better adhesion |
C. | Poor cohesion |
D. | Better cohesion |
Answer» C. Poor cohesion | |
8. |
Rolling of the sub-base material is done till ______ of the maximum density of the material. |
A. | 98% |
B. | 50% |
C. | 100% |
D. | 75% |
Answer» B. 50% | |
9. |
Which of the below is not a type of premix bituminous construction? |
A. | Bituminous concrete |
B. | Mastic asphalt |
C. | Penetration macadam |
D. | Carpet |
Answer» D. Carpet | |
10. |
Lateral confinement is provided by constructing ______ in advance. |
A. | Kerbs |
B. | Shoulders |
C. | Camber |
D. | Poles |
Answer» C. Camber | |
11. |
Which of the below is not involved in the preparation of the subgrade? |
A. | Compaction |
B. | Grading |
C. | Site clearance |
D. | Spreading |
Answer» E. | |