| 101. |
Which forms the basis for management control of software project? |
| A. | methods. |
| B. | tools. |
| C. | process. |
| D. | quality focus. |
| Answer» D. quality focus. | |
| 102. |
Zero duration activities but are assumed to start at the same time as thefirst and the end at the same time as the last one is called__________ activity. |
| A. | hijacked. |
| B. | heuristic. |
| C. | hammocked. |
| D. | hole. |
| Answer» D. hole. | |
| 103. |
__________ is record of how much the organization is willing to spend on thesystem. |
| A. | resource requirements |
| B. | functional requirements |
| C. | security requirements |
| D. | non functional requirements |
| Answer» B. functional requirements | |
| 104. |
_______ is a working model of one or more aspects of the projectedsystem. |
| A. | evolutionary model. |
| B. | v-process model. |
| C. | spiral model. |
| D. | software prototyping. |
| Answer» E. | |
| 105. |
The sub-characteristics of efficiency is ….. |
| A. | understandability. |
| B. | learnability. |
| C. | resource utilization. |
| D. | accuracy. |
| Answer» D. accuracy. | |
| 106. |
_________ activities on the network diagram have zero duration and use noresources. |
| A. | dangling. |
| B. | dummy. |
| C. | null. |
| D. | zero. |
| Answer» C. null. | |
| 107. |
Every risk is associated with a likely problem and an _______. |
| A. | activity. |
| B. | outcome. |
| C. | action plan. |
| D. | threats. |
| Answer» D. threats. | |
| 108. |
Herzberg's theory is ________. |
| A. | 3-factor theory. |
| B. | 6-factor theory. |
| C. | 2-factor theory. |
| D. | 1-factor theory. |
| Answer» D. 1-factor theory. | |
| 109. |
________ = risk likelihood X risk impact. |
| A. | risk estimate. |
| B. | risk expenditure. |
| C. | risk identification |
| D. | risk exposure. |
| Answer» E. | |
| 110. |
Risk Management consists of ____________. |
| A. | risk analysis and risk estimation. |
| B. | risk control and risk planning. |
| C. | risk identification and monitoring. |
| D. | risk control, planning, identification and monitoring. |
| Answer» E. | |
| 111. |
_______ is an activity bar chart indicating scheduled activity dates anddurations frequently augmented with activity floats. |
| A. | bar chart. |
| B. | ball chart. |
| C. | slip chart. |
| D. | gantt chart. |
| Answer» B. ball chart. | |
| 112. |
Projects lies between ___________. |
| A. | job & exploration |
| B. | methods & process |
| C. | quality & quantity |
| D. | tool& process |
| Answer» B. methods & process | |
| 113. |
The expectancy theory of motivation will focus on ________. |
| A. | instrumentality. |
| B. | reliability. |
| C. | reward. |
| D. | assignment specification. |
| Answer» B. reliability. | |
| 114. |
……………..is called if subsequent have the time by which an activity may bedelayed without affecting. |
| A. | action float. |
| B. | terminal float. |
| C. | free float |
| D. | null float |
| Answer» D. null float | |
| 115. |
UFP indicates ________. |
| A. | unused function points. |
| B. | unstructured function points. |
| C. | uniform function points. |
| D. | unadjusted function points. |
| Answer» E. | |
| 116. |
Find the two levels of development suggested by Booch ? |
| A. | micro and macro processes. |
| B. | inter and intra processes. |
| C. | internal and external processes. |
| D. | small and large processes. |
| Answer» B. inter and intra processes. | |
| 117. |
"Each activity has been scheduled to start at its earliest start date" is calledas_________. |
| A. | likelihood. |
| B. | activity schedule. |
| C. | probability. |
| D. | planning. |
| Answer» B. activity schedule. | |
| 118. |
________ is needed to ensure that the project remains under control andthat it continues to meet its business justification. |
| A. | yellow tape. |
| B. | white tape. |
| C. | red tape. |
| D. | black tape. |
| Answer» D. black tape. | |
| 119. |
The activities have zero duration but are assumed to start at the same timeas the first and the end at the same time as the last one is called__________activity. |
| A. | hijacked. |
| B. | heuristic. |
| C. | hammocked. |
| D. | hole. |
| Answer» D. hole. | |
| 120. |
A _________ contains a set of attributes that act as an aspect, quality,characteristic, or descriptor of the object. |
| A. | ordinary object. |
| B. | data object. |
| C. | template. |
| D. | instance. |
| Answer» C. template. | |
| 121. |
USDP means ________. |
| A. | unified software development process |
| B. | uniform software development process |
| C. | union software development process |
| D. | union software deployment process |
| Answer» B. uniform software development process | |
| 122. |
PRINCE means _____________ |
| A. | projects in combined energy |
| B. | projects in controlled energy |
| C. | projects in combined environments. |
| D. | projects in controlled environments |
| Answer» E. | |
| 123. |
_________ is the sub-characteristics of efficiency. |
| A. | understandability. |
| B. | learnability. |
| C. | resource utilization. |
| D. | accuracy. |
| Answer» D. accuracy. | |
| 124. |
The spiral model is originated by __________. |
| A. | b.w.boehm. |
| B. | b.w.williams. |
| C. | b.w.britto. |
| D. | b.w.hackman. |
| Answer» B. b.w.williams. | |
| 125. |
A Quality specification is otherwise known as ____________. |
| A. | allocation specification. |
| B. | alternate specification. |
| C. | attribute specification. |
| D. | assignment specification. |
| Answer» B. alternate specification. | |
| 126. |
The objective of ________ is to avoid or minimize the adverse effects ofunforeseen events. |
| A. | risk management. |
| B. | risk maintenance. |
| C. | risk taking. |
| D. | risky job. |
| Answer» B. risk maintenance. | |
| 127. |
CPM can be expanded as _______. |
| A. | control path method. |
| B. | critical path method. |
| C. | cohesion path method. |
| D. | control path model. |
| Answer» C. cohesion path method. | |
| 128. |
Ranking of the risks and determining risk aversion strategies is called________. |
| A. | risk analysis. |
| B. | risk control. |
| C. | risk identification |
| D. | risk evaluation. |
| Answer» E. | |
| 129. |
________ is some thing that is described by a set of attributes (data items)and that will be manipulated within the software (system). |
| A. | instance. |
| B. | class. |
| C. | object. |
| D. | data. |
| Answer» D. data. | |
| 130. |
KLOC indicates ___________. |
| A. | hundred lines of code. |
| B. | source lines of code. |
| C. | thousand lines of code. |
| D. | million lines of code. |
| Answer» D. million lines of code. | |
| 131. |
'Work expands to fill the time available" is _________ law. |
| A. | brooks. |
| B. | peters. |
| C. | parkinson\s. |
| D. | weinbergs |
| Answer» D. weinbergs | |
| 132. |
. In software prototype, partial working model is classified into ________. |
| A. | vertical and horizontal. |
| B. | vertical and straight. |
| C. | bended and horizontal. |
| D. | elevated and horizontal. |
| Answer» B. vertical and straight. | |
| 133. |
________ a set of attributes (data items) and that will be manipulatedwithin the software (system). |
| A. | instance. |
| B. | class. |
| C. | object. |
| D. | data. |
| Answer» D. data. | |
| 134. |
An Elaboration of Waterfall which stresses the necessity for validationactivities is known as __________. |
| A. | extended waterfall. |
| B. | iterative model. |
| C. | v-process model. |
| D. | spiral model. |
| Answer» D. spiral model. | |
| 135. |
________ is the diagrammatic form for Flow oriented Modelling. |
| A. | functional diagrams. |
| B. | er diagrams. |
| C. | data flow diagrams. |
| D. | system flow diagrams. |
| Answer» D. system flow diagrams. | |
| 136. |
_______ is a collection of projects that all contribute to the same overallorganizational goals. |
| A. | software. |
| B. | task |
| C. | programme. |
| D. | activity |
| Answer» D. activity | |
| 137. |
Expand the mnemonic SMART _________________ |
| A. | specific, measurable, achievable, relevant, time constrained. |
| B. | system, measurable, achievable, relevant, time constrained. |
| C. | specific, measurable, archive, relevant, time constrained. |
| D. | specific, measurable, archive, relevant, target. |
| Answer» B. system, measurable, achievable, relevant, time constrained. | |
| 138. |
Longer term benefits that are considered very difficult to quantify are called_______ . |
| A. | direct benefits. |
| B. | assessable benefits. |
| C. | indirect benefits. |
| D. | intangible benefits. |
| Answer» E. | |
| 139. |
_________ assesses the quality of a software product. |
| A. | acquirers. |
| B. | developers. |
| C. | independent evaluators. |
| D. | software designers. |
| Answer» D. software designers. | |
| 140. |
The organization as part of its monitoring and control policy may have a ________in place which dictates that certain statistics have to be collected at various stages of aproject. |
| A. | measurement programme. |
| B. | system programme. |
| C. | software programme. |
| D. | testing programme. |
| Answer» B. system programme. | |
| 141. |
CPM is an acronym for _______. |
| A. | control path method. |
| B. | critical path method. |
| C. | cohesion path method. |
| D. | control path model. |
| Answer» C. cohesion path method. | |
| 142. |
A ________ specification is concerned with how well the functions are tooperate. |
| A. | functional. |
| B. | quality. |
| C. | resource. |
| D. | scope. |
| Answer» C. resource. | |
| 143. |
Ranking of the risks and determining risk aversion strategies is called_______. |
| A. | risk analysis. |
| B. | risk control. |
| C. | risk identification. |
| D. | risk evaluation. |
| Answer» E. | |
| 144. |
In software prototype, partial working model is classified into ________. |
| A. | vertical and horizontal. |
| B. | vertical and straight. |
| C. | bended and horizontal. |
| D. | elevated and horizontal. |
| Answer» B. vertical and straight. | |
| 145. |
In product-driven projects, the objectives of the project are defined in terms of___________. |
| A. | functional requirements only. |
| B. | resource and non-functional requirements. |
| C. | functional and quality requirements. |
| D. | resource requirements only. |
| Answer» D. resource requirements only. | |
| 146. |
The problems experienced in the survey of managers published by Thayer,Pyster and Wood include_________. |
| A. | poor estimates and plans. |
| B. | poor role definition. |
| C. | poor quality control. |
| D. | both a and b. |
| Answer» E. | |
| 147. |
Which type of risk factor is most likely to cause problems for a softwareproject developing commercial software? |
| A. | inadequate user documentation. |
| B. | litigation expense. |
| C. | low productivity. |
| D. | cancellation of project. |
| Answer» B. litigation expense. | |
| 148. |
Closing the project involves _______. |
| A. | identifying next project. |
| B. | identifying the future ventures. |
| C. | identifying the faults. |
| D. | identifying follow-on actions. |
| Answer» E. | |
| 149. |
The project deliverable is supplied to customers release by release in a scheduledtime intervals is referred as |
| A. | agile |
| B. | incremental delivery |
| C. | v-process model |
| D. | spiral model |
| Answer» C. v-process model | |
| 150. |
In Software Prototype, ___________ means copies of input screens areshown to the users on a workstation, but the screens cannot actually be used. |
| A. | simulation. |
| B. | annealing. |
| C. | mock-ups. |
| D. | rad system. |
| Answer» D. rad system. | |