1.

Works overhead is Rs 40,000, total machine hours is 8500 hours and time allowed for machine setting is 500 houRs What is the machine rate?

A. s. 2 per hour
B. s. 3 per hour
C. s. 4 per hour
D. s. 5 per hour
Answer» E.