1.

Which one of the following is relevant in normal circumstances in determining the amount of damages for breach of contract?

A. Normally expected loss
B. Difference between market price and contract price
C. Sudden closure of production
D. Additional expenses for procuring the goods
Answer» B. Difference between market price and contract price


Discussion

No Comment Found