Which of the following is least likely to contribute to developing an effective project team supportive of quality? |
A. | Commitment to the project |
B. | Team member flexibility |
C. | Frequent turnover of personnel |
D. | Team interest in workmanship |
Answer» D. Team interest in workmanship | |