| 1. |
Where a party to a contract fails to perform at or before a specified time and it was the intention of the parties that time should be of the essence |
| A. | The contract becomes voidable |
| B. | The contract does not become voidable but the aggrieved party is entitled to compensation |
| C. | The contract becomes void |
| D. | None of these |
| Answer» B. The contract does not become voidable but the aggrieved party is entitled to compensation | |