| 1. |
What is the UCL of the standardized R chart for short production runs? |
| A. | D<sub>4</sub> |
| B. | D<sub>5</sub> |
| C. | D<sub>1</sub> |
| D. | D<sub>2</sub> |
| Answer» B. D<sub>5</sub> | |