1.

What is the UCL of the standardized R chart for short production runs?

A. D<sub>4</sub>
B. D<sub>5</sub>
C. D<sub>1</sub>
D. D<sub>2</sub>
Answer» B. D<sub>5</sub>


Discussion

No Comment Found