| 1. |
What is the time for a typical cycle, including charging the feed, crystallization, and removal of the magma? |
| A. | t1 hour |
| B. | t2-8hr |
| C. | t7-15hr |
| D. | t5-14hr |
| Answer» C. t7-15hr | |