1.

What does the critical path in PERT represent ?1. The shortest path for the earliest completion of the project.2. The longest path of the network from the initial to final event,

A. 1 only
B. 2 only
C. Both 1 and 2
D. Neither 1 nor 2
Answer» C. Both 1 and 2


Discussion

No Comment Found

Related MCQs