Two piles, one a bored cast-in-situ pile and another a precast driven pile, both of same length and diameter are constructed in a loose sand deposit. If the bearing capacity of the bored pile is , and that of the precast driven pile is , then which of the following is correct ?

A. >
B. =
C. <
D. No specific comparison may hold good
Answer» B. =