1. |
Total float for any activity is defined as the difference between%! |
A. | Its latest finish time and earliest start time for its successor activity |
B. | Its latest start time and earliest start time |
C. | Its latest start time and earliest finish time |
D. | Its earliest finish time and earliest start time for its successor activity |
Answer» C. Its latest start time and earliest finish time | |