1. |
The project manager leads a project team that is comprised of many different skills anddisciplines. He must use an exceptional number of negotiating skills because he __________. |
A. | is expected to discuss all facts of the technical parameters of the project. |
B. | will be leading individuals without having direct control over them |
C. | will encounter the shoptalk of each unique discipline |
D. | will be using these skills to keep from accepting additional work. |
Answer» C. will encounter the shoptalk of each unique discipline | |