MCQOPTIONS
 Saved Bookmarks
				| 1. | 
                                    The net cash flows of the project and their present values are as follows Year 1 2 3 4 Net cash flow (Rs) 5100 5100 5100 7100 PVIF @12% 0.893 0.797 0.712 0.636 Present Value (Rs) 4554 4065 3631 4516 The initial investment in the project is Rs12500, What is the NPV of the project? | 
                            
| A. | 4066 | 
| B. | 4166 | 
| C. | 4266 | 
| D. | 4566 | 
| Answer» D. 4566 | |