The following operations are required for tunnelling in rocky terrain : 1. Removing the foul gases 2. Marking the tunnel profile 3. Setting up and drilling 4. Checking misfire 5. Mucking The correct sequence is : |
| A. | 1 2 3 4 5 |
| B. | 2 3 5 4 1 |
| C. | 4 2 1 3 5 |
| D. | 2 3 1 4 5 |