The correct sequence of these operations in tunnel construction is______________?_x005F_x000D_Consider the following operations :_x005F_x000D_1. Drilling_x005F_x000D_2. Blasting_x005F_x000D_3. Mucking_x005F_x000D_4. Placing steel_x005F_x000D_5. Placing concrete |
A. | 1,2,4,3,5 |
B. | 1,3,2,4,5 |
C. | 1,2,3,4,5 |
D. | 1,3,4,2,5 |
Answer» D. 1,3,4,2,5 | |