MCQOPTIONS
Saved Bookmarks
1. |
The correct sequence of these activities is________________?_x005F_x000D_Consider the following activities in a building construction?_x005F_x000D_1. Concreting of roof slabs_x005F_x000D_2. Brick-jelly lime concrete terracing_x005F_x000D_3. Erection of form work for slab_x005F_x000D_4. Construction of parapet wall in terrace |
A. | 1,3,2,4 |
B. | 3,1,4,2 |
C. | 3,1,2,4 |
D. | 1,3,4, 2 |
Answer» D. 1,3,4, 2 | |