The bond stress at intermediate points is resisted..
1.
The bond stress at intermediate points is resisted by:
A.
Friction
B.
Shrinkage
C.
Adhesion
D.
Anchorage
Answer» D. Anchorage
Show Answer
Discussion
No Comment Found
Post Comment
Related MCQs
The shearing resistance is also termed as __________
At intermediate points along the length of a beam, the bond stress is resisted by __________
The term transmission refers to attainment of uniform __________
The steel and concrete reach their maximum values of stress when bond stress is?
The bond stress at intermediate points is resisted by __________
The bond stress in the prestress members is mainly due to __________
The swelling of the wire produces which action on concrete?
In a pretensioned system, when a wire is released from its temporary anchorage the end of the wire swells as a result of __________
AT_INTERMEDIATE_POINTS_ALONG_THE_LENGTH_OF_A_BEAM,_THE_BOND_STRESS_IS_RESISTED_BY:?$
The shearing resistance is also termed as:$
Reply to Comment
×
Name
*
Email
*
Comment
*
Submit Reply