MCQOPTIONS
Saved Bookmarks
| 1. |
The amount paid to sub-contractor is ________. |
| A. | ubtracted from the contract price |
| B. | ebited to contract a/c |
| C. | redited to contract a/c |
| D. | dded with the contract price |
| Answer» C. redited to contract a/c | |