Suppose a project has many hazards that could easily injure one or more persons and there is no method of avoiding the potential for damages. The project manager should consider __________ as a means of deflecting the risk. |
| A. | abandoning the project |
| B. | buying insurance for personal bodily injury |
| C. | establishing a contingency fund |
| D. | establishing a management reserve |
| Answer» C. establishing a contingency fund | |