| 1. |
Risk Mitigation is a Risk _______ Activity. Risk Monitoring is a _____ Activity. |
| A. | Avoidance, Project tracking. |
| B. | Increasing, Project tracking. |
| C. | Project tracking, Avoidance. |
| D. | Random, Tracking. |
| Answer» B. Increasing, Project tracking. | |