MCQOPTIONS
Saved Bookmarks
1. |
PP & PPK is calculated for i. Initial production run ii. Future production iii. Initial process setting The correct order is |
A. | i & ii |
B. | ii & iii |
C. | i & iii |
D. | i, ii & iii |
Answer» D. i, ii & iii | |