Pick up the correct step used for scheduling a project by C.P.M.__________________? |
A. | a project is divided into various activities |
B. | required time for each activity is established |
C. | sequence of various activities is made according to their importance |
D. | network is drawn by connecting the activities and the events |
E. | all of the above |
Answer» F. | |