MCQOPTIONS
Saved Bookmarks
1. |
%_Pick up the correct statement from the following with regards to C.P.M. network analysis of projects_% |
A. | The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time |
B. | The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time |
C. | Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity |
D. | All the above |
Answer» E. | |