MCQOPTIONS
Saved Bookmarks
| 1. |
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is |
| A. | 20 |
| B. | 25 |
| C. | 35 |
| D. | 15 |
| Answer» C. 35 | |