MCQOPTIONS
Saved Bookmarks
1. |
Mobilization advance up to 10% of the cost of work is given to a contractor_______________? |
A. | on commencement of work at site for payment of loan taken by him |
B. | for the purchase of construction materials |
C. | for the payment of advances to labour and other staff |
D. | for all activities required to start the work at site on finalization of the contract document |
Answer» E. | |