MCQOPTIONS
Saved Bookmarks
| 1. |
is the time by which the completion of an activity can be delayed beyond its earliest finish time without affecting the earliest start time of a succeeding activity |
| A. | slack |
| B. | total float |
| C. | free float |
| D. | independent float |
| Answer» D. independent float | |