In time-cost optimization of a project, crashing is done____________? |
A. | on all the activities |
B. | on all the activities lying on the critical path |
C. | only on activities lying on the orginal critical path and having flatter cost slopes |
D. | on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope |
Answer» E. | |